R45 road closure

18 August 2025 | by  

Notice of 24 hr stop / go on the R45 for next 3 months mid-August 2025 - end December 2025

Franschhoek Pass
 TypeActivityStartEndStart DateEnd Date
124 hour closureSlip Repairs, Asphalt PatchingFranschhoekMount RochelleMid-August 2025December 2025
2Day ClosureWater PipesMedi CentreMercedesMid-August 2025December 2025
324 hour closureService ducts, Vrede & Lust Intersection
 
Vrede & LustAgrimarkMid-August 2025December 2025

Starting with the Franschhoek Slip repairs. Day closures for water pipes relocation at old Paarl Road. 24 Hour closure between Vrede & Lust and Agrimark to build culverts across the road.